Although such periods of storm covered, the the project is still trying to concentrate on human resources to accelerate M&E progress keeping up the construction progress.
According the weekly record from 23/5 to 29/5/2016), the project is roll-finishing on schedule on the 2nd floor and the 3rd floor, including mounting lights, socket switches, detectors, sanitary equipment, air ventilation, fans, electrical panels and testing the finished floors. Uniform schedule of executing M&E works as follow:
- Fabrication and installation workshops Sleeve in-progress pouring concrete formwork transplant
- Installation of drainage pipe system
- Installation of a fire hose system
- Installation of conduit piping and cable tray
- Installation of copper pipe and wind pipe
- Coating and putting through the wall sleeve
- Waterproofing
- Closed pipeline testing