Constructive acceleration at Haseko Project

30/05/2016

Understand the expectations from the investor and board of directors of the company, all members of the project management of Haseko have been focusing in all best resources to accelerate the project schedule.

Although such periods of storm covered, the the project is still trying to concentrate on human resources to accelerate M&E progress keeping up the construction progress. 
According the weekly record from 23/5 to 29/5/2016), the project is roll-finishing on schedule on the 2nd floor and the 3rd floor, including mounting lights, socket switches, detectors, sanitary equipment, air ventilation, fans, electrical panels and testing the finished floors. Uniform schedule of executing M&E works as follow:
  • Fabrication and installation workshops Sleeve in-progress pouring concrete formwork transplant
  • Installation of drainage pipe system
  • Installation of a fire hose system
  • Installation of conduit piping and cable tray
  • Installation of copper pipe and wind pipe
  • Coating and putting through the wall sleeve
  • Waterproofing
  • Closed pipeline testing

Other articles

Partners
pn1
pn2
pn3
pn4
pn5
pn6
pn7
pn8
pn9
pn10
pn11
pn12
pn13
pn14
pn15
pn16
pn17
pn18
pn19
pn20
pn21
pn22
pn23
pn24
pn25
pn26
pn27
pn28
pn29
pn30
pn31
pn32
pn33
pn34
pn35
pn36
pn37
pn38
pn39
pn40
pn41
pn42
pn44
pn45
pn46
pn47
pn48
pn49
pn49