Currently, the project’s steering committee is still determined focus on mobilizing human resources and accelerate the construction of the remaining items evenly over all areas.
In the coming weeks from May 9th 2016 to May 16th 2016, the project is concentrating on the following tasks:
- Installing electrical system: cut chisels and install conduit pipe inground, sound wall; installation of rack and floor cable trays, axial cable tray, drag and insert electrical wire at tower N01, N02, N03, HH01.
- Installing plumbing system: installation of drainage pipes, ventilation, check the drainage tube leakage; waterproofing drainage tube for apartments, installation of water supply pipes in the ceiling apartments; cut chisels and insert water supply; installation of pumping equipment in van.
- Installing fire system: installation of fire mains, fire pipeline pressure testing; installation of fire valves, installation of equipment and cabinets fire nozzles.
- Construction of the ventilation system: production of construction and installation of the wind pipe, installation of air valves, vent holes and ventilators.
On the construction site, working atmosphere is always engrossed and absorbed, despite the hot weather. With wide project areas, safety supervision section of the project are regularly patrolling, checking the site daily, while waring of the rick of insecurity to overcome early handling.