Record of weekly activities at Sonasea Villas and Resort Phu Quoc site

04/05/2016

Sigma Engineering is performing M&E works of 51 Villas & Shophouse at Sonasea Villas and Resort Phu Quoc site to hand over on schedule to the clent in the end of June 2016.
 

51 Villas

This record describes the activities for the week of 25 April – 04 May 2016 and includes:
Lot SV3
Wiring, piping & checking insulation; complete installation of drainage pipes for all 33 units of 3key, 6 units of 2key.
Concealed piping íntallation, wiring exposure, ELV & fire alarm, wires for lighting, lectrical power and ELV,
carrying out the inspection of short circuit parameters, insulation for lamps, sockets, ELV of 7 units of 4 key.
Installing louvers for all units of 3key.
Complete enclosed test, pressure test for drainage systems and water supply for 33 units 3 key and 6 units 2key.
Installing uPVC & PPR for plumbing system connecting to external infrastructure of units.
Completing installation of copper pipes, ducts, wind boxes for 05 units 4 key, 02 units 4 key.
Completing closed test for 2 units of 3key.
Installing drain pipes, ducts, wind boxes for 1 unit 5key.
Shophouse SS01
Wiring exposure for electrical system, ELV, fire alarm, wiring for lamps, electrical power and ELV, 
checking circuit measurement, isulation for ELV; installing uPVC & PPR for plumbing system of floor 1,2,3,4 axes 5-8; 

Toolbox Meeting


Other articles

Partners
pn1
pn2
pn3
pn4
pn5
pn6
pn7
pn8
pn9
pn10
pn11
pn12
pn13
pn14
pn15
pn16
pn17
pn18
pn19
pn20
pn21
pn22
pn23
pn24
pn25
pn26
pn27
pn28
pn29
pn30
pn31
pn32
pn33
pn34
pn35
pn36
pn37
pn38
pn39
pn40
pn41
pn42
pn44
pn45
pn46
pn47
pn48
pn49
pn49