Update progress on Wyndham Soleil Da Nang in the 12th week

30/03/2018

Wyndham Soleil Da Nang is designed to be inspired by the waves of cool sea, located at the golden position at Pham Van Dong intersection, Phuoc My crossroad, Son Tra District, Da Nang. With the meticulous invested, after completion, Wyndham Soleil Da Nang will be the new center of Central Vietnam.

Known as the tallest building complex in Danang and the most beautiful beach location in Vietnam, the project is planned on a land area of 2.2 hectares including a hotel and three five-star Condotel Hotel Apartments with a comfortable and high-end business center promising to bring customers a classy life. Sigma – the main M&E Contractor of the project is honored to be believed by the investor to provide and install M&E services for the project. With Wyndham Soleil Da Nang, Sigma will bring in the abundance of life, lighting up the sparkling lights so that Soleil became the "lighthouse on land."
Last week, from March 19th to 24th, 2018, Sigma has been deploying the main M&E works such as:
  • Brick wall cutting and conduit installation - levels 10-14
  • Wiring work on level 6
  • Lighting equipment and outlets installation - Level 4 - mockup room
  • Copper pipe and condensate pipe installation - levels 10-17
  • Coring work and water supply pipe installation levels 10-
  • Sanitary equipment installation on level 4
  • Water drainage pipe installation- level/ level 3
Next week, Sigma will execute the main works such as:
  • Brick wall cutting and conduit installation - levels 12-16
  • Wiring work on level 6
  • Lighting equipment and outlets installation - Level 4 - mockup room
  • Copper pipe and condensate pipe installation - levels 12-19
  • Coring work and water supply pipe installation levels 12-16
  • Sanitary equipment installation on level 4
  • Water drainage pipe installation- level/ level 3
Some pictures at the project:
 

Overview of the Wyndham Soleil Da Nang
 

Doing exercise - Tool Box Meeting early in the morning


Materials at the storage are neat and clear

 
Brick wall cutting/ wiring work


Check out the drawings, wiring work on the ceiling

Other articles

Partners
pn1
pn2
pn3
pn4
pn5
pn6
pn7
pn8
pn9
pn10
pn11
pn12
pn13
pn14
pn15
pn16
pn17
pn18
pn19
pn20
pn21
pn22
pn23
pn24
pn25
pn26
pn27
pn28
pn29
pn30
pn31
pn32
pn33
pn34
pn35
pn36
pn37
pn38
pn39
pn40
pn41
pn42
pn44
pn45
pn46
pn47
pn48
pn49
pn49