Honored to implement the M&E works for the project since 11/2015, Sigma has been accomplished the progress. From 2nd March to 08th March, the project has implemented some typical works:
- Install sleeve on slab of 28th floor
- Install drain pipe for Hotel area at 18 ~ 19th floor
- Install drain pipe for apartment area at 18 ~ 19th floor
- Install drain pipe in riser for podium area
- Installing cable ladder at hotel area - 14th floor
- Install PVC pipe at Hotel area - 13th ~ 14th floor
- Pressure test water supply-drain pipe at 3th ~ 5th floor
- Wiring ELV & ELE cable system at hotel area - 13th, 14th floor
- Install water supply pipe for Apartment area at 15th ~ 16th floor
- Install water supply pipe in riser for Hotel area at 13th ~ 20th floor
- Install water supply pipe for corridor area at 12~13th floor