After Lunar New Year, the Steering Committee is urging the engineers and workers at Four Points by Sheraton Da Nang to accelerate the construction while continuing to ensure the progress and commitment to the investor. From the 6th of February to the 11th of February 2017, many categories have been completed as scheduled, such as:
- Dragging the electrical cables, extra low voltage at 08th ~ 22nd floor
- Accepting water supply and drainage systems at 07th ~ 30 floor
- Closed testing procedures in water supply and drainage systems at 6th floor in apartment area
- Accepting ventilation system at 07th ~ 30th floor
- Installing wind pipes, ventilators at 6th floor in apartment area
- Installing wall pipe of electrical systems at 10th ~ 30th floor in hotel area
- Installing HVAC systems at 8th ~ 30th in hotel area
In the coming weeks, the project will continue to implement other categories such as:
- Constructing Busway pipe
- Craning Chiller pipe at 5th floor
Here are some photos at Four Points by Sheraton Da Nang project:
Intallation of electrical pipes at 31th floor Installation of electrical pipes at 20th in hotel area
Craining steel pipes