Up to now, the project manager is strengthening inspection, while urging the engineers and workers to strictly observe the progress and quality of construction. From 2nd January to 07th January 2017, the project was initially implemented the following works:
- Installing underground pipe and backfilling the ground
- Submit MSA for MV switch-board
- Submit MSA for transformer
- Submit MSA for pump firefighting
- Submit shop drawing for substation layout
- Submit shop drawing for request opening and louver at Utility – HVAC system
Here are some first photos of Swire Cold Storage Vietnam:
Underground pipe installation in Utility
Connecting water drainage pipeline in Utility
Backfilling the ground after installing underground pipe
Detailed information of the project: