The project’s steering committee is attempting to complete the remaining works. In the first two weeks of 2017, the project is focusing on the following tasks:
- Installing electrical system: installation of Electrical Cabinet 1,2; lighting system at Tunnel 1; installation of medium voltage cables; installation of cable tray at Tower N02; drag fire alarm cables, speaker cables at Tower N03, HH01; cut chisels and install conduit pipe in sound wall at Tower HH01.
- Installing plumbing system: installation of drainage pipes, ventilation, check the drainage tube leakage; waterproofing drainage tube for apartments, installation of water supply pipes in the ceiling apartments; cut chisels and insert water supply; installation of pumping equipment in van, alignment of drainage pipes at Tower N01, N02, N03, HH01.
- Installing fire system: installation of fire mains, fire pipeline pressure testing; installation of fire valves, installation of equipment and cabinets fire nozzles at Tower N01, N02, N03 and HH01.
- Installing the ventilation system: construction and installation of the wind pipe, installation of ventilators at Tower N01, N02, N03 and HH01.