At the end of November 2016, Sigma has completely installed waste water drain pipe for Apartment area at 10th floor and also fully installed firefighting pipe for Apartment area at 9th floor following rigorous standards. In the first half of December 2016, Sigma will install water supply for kitchen at 5th floor and complete ELE & ELV systems for the building.
Here are some site photos of SHP Plaza Hai Phong:
Install Chiller pipe at 7th floor
Install PVC conduit in column and wall at zone 3 – 15th floor, zone 1 – 18th floor