Despite more than one month since taking over the project, the staff are striving to confirm Sigma reputation in providing M&E services for the buildings and factories. In these days, despite the harsh weather conditions, the project steering committee are trying to accelerate the construction while continuing to observe the strict requirements and quality from the investor.
In the previous week, from 6th February to 11th February 2017, the project was initially implemented the following works:
- Inspecting temporary panel system
- Installing underground pipe – HDPE pipe
- Painting firefighting system
- Receiving and arranging materials in site
- Processing to manufacture for working
- Making manhole for water drainage system
- Installing earth rod and bare copper for earthing system
- Concreting manhole for water drainage system
Here are some photos at Swire Cold Storage Vietnam project:
Inspecting temporary panel system Painting firefighting system
Receiving and arranging materials in site Installing earth rod and bare copper for earthing system