Located at No.265 Cau Giay, FLC Twin Towers is built on a total area of 10,629 m2, including 50 floors of apartment towers, 38 floors of office tower, six floors of commercial center and four basement garages will be executed under the talented hands of Sigma workers.
Officially became the Main M&E Contractor of FLC Twin Towers on June 08th, 2017, after nearly one year of executing, Sigma completed many M&E works in parallel with finishing the of the project. Last week, the project mobilized large number of manpower, including 170 highly skilled workers and nearly 20 experienced engineers, to speed up the progress as well as meet the strictest requirements from the investor. From 07/05 to 12/05/2018, the quantity of performed works as follows:
- Apartment block:
- Finished construction of civil works” level 7th ~ 27th and 29th ~ 47th
- Conduit installation and wiring work: level 48
- Sanitary equipment installation: level 8~10
- Basement area:
- Water drainage pipes installation Basement 2, 3, 4
- Water supply pipes installation Basement 2, 3, 4
- Wiring work for Basement 2, 3, 4
- Recessed lighting installation Basement 4
- Busway, electrical cable tray installation and busway installation from MSB to MBA
- Chiller installation Basement 2
- Office block:
- Executing from level 7~22
Some pictures of the project last week:
Overview of FLC Twin Towers project
Tool Box Meeting daily at the project
Conduit installation at the commercial area/ Duct installation at the office area
Chiller installation at the podium area
Safety training for workers at the site office