Honored to implement the project from the beginning of 2017, Sigma – M&E Main Contractor of the project is still fulfilling the tasks assigned, worthy of trust from partners. Now, with dozens of workers and more than 20 Sigma engineers are working day and night, the project not only promises to meet the schedule, but also ensures the safety, aesthetics and quality as committed to the owner. Sigma is confidently co-operating with other famous units in implementing the project such as: Nihon Sekkei, Coninco…
Compared with the schedule, Sigma has gone halfway through. Last week, from March 25th to April 5th, 2018, the main works were being implemented at the project such as:
- Installation of supply duct - Basement 3 ~ mezzanine
- Installation of cable tray and trunking from Level 6 to Level 10
- Installation of water supply pipe, and carrying out pressure test L6 -10
- Installation of water drainage pipe, and carrying out leakage test from Level 10 to L10
- Wiring work for FA, PA, CCTV, BMS and switches from L6 to L10
- Completion of generator room
Some photos of the project:
Overview of the MB Grand Tower project
Tool Box Meeting daily at the project
Installation of lighting conduit from L6~L10/ Electrical cable pulling for lift - Basement 1
Installation of lighting conduit L25/ Installation of conduit and wiring for HVAC system level 24