Yen Tu Festival and Tourism Center can be considered as the main door welcoming visitors. Stepping through the three-step staircase of the project, visitors will officially start the pilgrimage road to the sacred Yen Tu with emotional experiences when passing through the architectural items that have formed such as Reception Area, Festival Center, Conference Hall, Showroom, Management Authority Area, Resort & Resort, Service Area ...
With abundant human resources at the project, including nearly 70 skilled workers and more than 10 experienced engineers, Sigma has been doing well the role of the Main M&E Contractor, worthy of trust and the trusted from the investor - Tung Lam JSC. Over a year of implementation, many works executed by Sigma has been completed. Last week, from April 16 to April 22, Sigma has completed the main items such as:
Electrical work:
- Hotel block
- Installation of electrical conduit on level 1 of resident block
- Installation of conduit and wiring work for ELV system on level 1 of resident block
- Wiring work on level 1 of resident block
- P1 area
- Installation of conduit and wiring for fire alarm system
- Installation of conduit and wiring work for ELV (extra low voltage) system
Mechanical work:
- Ductwork
- Ductwork at C3
- Installation of ventilation fans
- Installation of air grilles
- Chiller system
- Installation of chiller pipes
- Chiller pipe insulation assembling
- Mechanical work on level 1- P1
- Installation of copper pipe
- Installation of air duct
- Installation of FCU
- Installation of outdoor unit
- Hotel rooms - C3
- Installation of chiller pipe, risers and equipment in technical room
- Installation of HVAC system
- Ductwork fabrication
- Installation of air duct
- Installation of air grilles and dampers
Some pictures at the project last week:
Overview of Yen Tu project
Working atmosphere at Yen Tu site office
Tool Box Meeting Daily
Materials in the storage are arranged in separate systems
Installation of electrical system at C2/ electrical system at P5
Installation of air conditioning system at P4/ P5