The story of concrete, trees or the journey of reintegration of people into nature was written by the architect - Vo Trong Nghia and the talented hands of Sigma workers through the Chic-land Hotel project.
Chic-land Hotel is redefining the concept of "comfort" in an impossible way. "Comfort in nature" is the way that the owner - Chic-Land JSC wants to show to bring the best and the most complete experience. In here, Chic-land wants to bring the soul of “Eco-chic”. The local natural materials such as basalt, sandstone, bamboo ... are fully utilized to keep pace with the spirit of Eco-chic. Covering the Chic-land Hotel will be the gentle green and pure of grass, turning the whole project into a quiet oasis in the beautiful white sand of My Khe beach.
With an outstanding ability, Sigma is ready to accept Chic-land as an interesting challenge due to the strict requirements in the process of research and treatment, meticulous when applying the new technology in the process of execution. The clever combination of greenery and environmentally friendly appliances will provide a supreme balance between comfort and nature. The design of a classy architecture is the perfect M&E system created by the hands of the Sigma workers, has long been the trademark. All will be ensured that every guest's experience at this place will be uplifted.
Last week, Sigma maintained a staff of more than 20 employees to ensure the progress of the project. It is expected that in early September, Sigma will mobilize more human resources to meet the progress of the project. From 13/08 to 19/08/2018, the main works were being implemented in the project last week as:
- Electrical system
- Installation of cable ladder
- Wiring works
- Installation of medium voltage, low voltage
- HVAC system
- Installation of copper and drainage pipes
- Insulation for copper pipes
- Installation of HVAC system
- PL system
- Insulation for hot water pipes and drainage pipes
- Installation of sanitary equipment
Some pictures of the project last week:
Overview of Chic-land Hotel project
TBM daily at the project
Sigma engineers at the site office
Execution of civil works on level 2
Sleeve installation on level 1~5