Identified as one of the key cultural projects, the project implementation process has been designed by the world’s leading architects. With the importance of the building, the investor always asked the contractors to accelerate the progress, finished before Yen Tu Spring Festival 2018, contributing to serve 710 years of King Tran Nhan Tong attained Nirvana and 2018 National Tourism Year hosted by Quang Ninh.
Honored to implement the project from middle of April, 2017, Sigma has been doing well the task of a leading M&E Contractor in Vietnam. From the week of 24th to 28th July, 2017, the typical works were being implemented such as:
- Chipping and installation of PVC Conduit in the hotel rooms
- Chipping and installation of PVC Conduit in the corridor of the floor, wiring
- Pulling and wiring the electrical cables at the mock-up apartments
- Pulling and wiring the electrical cables at the hotel rooms
- Installation of PVC conduit and wiring cables for the fire alarm system
- Installation of firefighting system
- Executing air duct for P1 area
- Installation of Chiller pipes
- Installation of copper pipes
- Installation of wind pipes
- Installation of Chiller pipes and risers in the hotel rooms.
Here are some photos of the project last week:
Project overview – Information Area
Project overview- Hotel area and festival ground
Tool Box Meeting at the project
Chipping – 1st floor – C3A, Hotel area / Installation of HVAC system at C3C tunnel – Hotel area
The warehouse area is neatly organized
Working atmosphere at site office of Yen Tu project