Updated the M&E progress of Movenpick project (Infrastructure package) in the 36th week
11/09/2018
Phu Quoc has long been known for its mild climate with 300 sunny days per year right in the Gulf of Thailand so there is almost no storm. This creates favorable conditions for tourism development throughout the year. This is a rare occurrence, as tourism in the North or Central - the two most commonly visited tourist places in Vietnam are frequently occurred the storms in July and August, which have a great impact on the domestic and international tourism. Movenpick Resort, is in a beautiful location at Ong Lang Beach, Cua Duong Commune, Phu Quoc District, Kien Giang Province - which inherits all-natural privileges in Phu Quoc Island. Not only that, Ong Lang Beach also offers visitors a wonderful experience with long and white sand, soft waves like a cuddle and pleasant climate that is never found anywhere.
The investor – Cua Duong Star JSC has undergone rigorous selection to ensure quality and progress for the project is always timely. With a strong financial and a great competence, Sigma has proven its superiority as an M&E Contractor at Movenpick Resort. The installation of M&E services of the project is divided into two categories: Resort area and Infrastructure area. Sigma always ensures safety, quality, aesthetics to bring the project to the schedule.
With a strong financial and great capability, Sigma has demonstrated its superior capabilities as an M&E contractor for Movenpick Resort. The installation of M & E services of Sigma project is divided into two categories: Resort and Infrastructure. Sigma always ensures safety, quality, aesthetics to meet the project’s progress.
Last week, from 3rd September to 08th September, the Infrastructure package of Movenpick project has maintained its human resources at over 10 experienced engineers and more than 30 skilled workers to ensured that the main works were always committed to the owner. The following works were being implemented at the project last week:
Electrical works
Installation of lighting control systems for the N2 line
Installation of sleeve pipes at the technical house – Zone A
Installation of sleeve pipes at T5-T6 area
Installation of PVC 32 (earthing leads) at T1 area
Mechanical works
Manhole fabrication at the Hotel area
Drainage pipe fabrication at the Hotel area
Pouring the concrete at the Hotel area
Manhole fabrication at the Villa area
Here are some photos of the project last week:
Overview of Movenpick project in the 36th week
Tool Box Meeting daily at the project
Materials on site were divided into separate systems
Medium voltage installation, information system installation at T5-T6 area