During 9 months of construction, the M&E works in the project have always been focused by Sigma, and always fulfilled the responsibility as committed to the investor. Each system implemented by Sigma will fully meet the technical requirements, synchronize the facilities with the equipment in the building. Once in operation, Doji promises to contribute to beautify the landscape of the regional architecture and make a highlight in the city center.
Although the weather was somewhat erratic, Sigma workers still worked hard to complete the committed schedule with the investor. Last week, typical works were being implemented at the project such as:
- Electrical works:
- Installing PA, FA system equipment from level 10 ~ 15
- Installing electrical system from level 6 ~ 9
- Electrical cable pulling from level 1 to 5
- HVAC works:
- Installing Chiller system, Chiller pump room, cooling tower
- Ductwork and ventilation fans installation on the roof
- Duct installation on level 1~5
- Air grille installation on level 6~9
- Plumbing & FF work:
- Fire protection cabinet installation from level 6~9
- Fire extinguisher installation at basement 2, 3
Some photos of the project last week:
Doji precious stone are gradually completed
TBM daily at the project
Working atmosphere at the site office
Electrical cabinet installation at level 2/ Air grile installation at level 7
Electrical wire system installation from level 6~9/ Duct installation on level 3