The “poetry” and the “love” of Hai Phong seems to dispel the erratic weather in the early summer, to encourage the motivation of Sigma employees who are working in SHP Plaza here, help them work more enthusiastic, more zeal to keep up with the schedule as committed to the client.
After nearly two years of designing and deploying M&E works of the project, Sigma is still fulfilling its mission. Last week, from April 13th to April 20th, the typical works were being implemented such as:
Electrical system:
- Wiring cable for generator room on the 1st floor
- Wiring ELV & ELE at apartment area on the 10-16 floor
- Install cable ladder for generator room on the 1st floor
- Install cable ladder in riser
- Complete the cable connection on the 5th floor
- Constructing cable ladder for corridor on 23-24 floor
- Install busduct in riser
- Wiring cable at 15-16
- Chip the 23-24 floor, zone 3
Plumbing system:
- Install water supply pipe at apartment area on the 17th floor
- Install water supply pipe in wall at hotel area on the 19th floor
- Chip, install water supply pipe at hotel area on the 20th floor
- Install water drainage pipe at 22-23 floor
- Install water supply pipe in riser
HVAC system:
- Pressure test for Chiller pipe on the 6th floor
- Insulate, install ventilators on the 8th floor
- Install Chiller pipe on the 5th floor
- Constructing ventilators on the 18th, 19th, 22nd floor
Fire Fighting system:
- Install Firefighting pipe at apartment area on the 21st floor
- Install Firefighting pipe at hotel area on the 20th, 21st floor
- Install Firefighting pipe at hotel area on the 23rd floor.
Here are some photos of the project:
Overview of SHP Plaza Hai Phong
Installation of HVAC System