The hospital will consist of more than 20 specialties such as Orthopedic Traumatology, Pediatrics, Obstetrics and Gynecology, Endocrinology, Cardiovascular, Surgery…. combining technology and expertise with superior quality and superior customer service.
With the approval of the Prime Minister, Hanoi French International Hospital was officially renovated, extended and built a new building to complement the functions of the hospital with a total of over 170 beds, meeting the demand for medical treatment for people inside and outside the capital.
With a total investment of more than $56.67 million, Hanoi French International Hospital Co., TLD – the investor of the project has been carefully and meticulously in the selection of the contractors, especially the construction contractor and M&E contractor for the project, ensuring the strictest criteria in architectural planning in accordance with the management regulations, construction master plan of Hanoi, is expected to complete by the end of 2018.
Receiving the trust from the investor, Sigma has been doing the good role as the contractor of M&E Main Contractor. This week, from 21st to 25th August 2017, the project is implementing the following works:
- Marking and sleeve installation of L4 – Zone 3
- Embedded conduit installation of L5 – Zone 1
- Embedded conduit installation of L5 – Zone 2
- Embedded conduit installation of L5 – Zone 3
- Embedded conduit installation of L6 – Zone 1
Here are some photos of the project:
Daily Tool Box Meeting at the project
Marking and sleeve installation
Site office in the 16th week
Storage area is neatly organized