M&E installation progress at Lancaster Luminaire project
30/06/2021
Located at a prime location at 1152-1154 Lang Street, Lancaster Luminaire has made a difference in the real estate market as a civilized, modern, and luxurious residence according to European standards. Here, the residents will enjoy unique services and utilities, bringing an ideal and convenient life thanks to its location near the connection point to the city center.
The project has a total area of 6,056.4 m2, including a 25-storey tower and will provide about 300 luxury apartments to the market. With a luxurious and sophisticated design structure, residents at the project will enjoy a fresh green living space and perfect utility services such as an outdoor swimming pool, gym, commercial center, supermarket, green campus, children's play area....
As a reputable M&E general contractor, Sigma is continuing to implement the Lancaster Luminaire project to create the best quality products, ready to hand over to customers. Currently, the works that we are working on include:
- Water supply and drainage system:
- Insulating sleeve for drainage system on the 12th floor
- Installing sleeve for drainage system on the 12th floor
- Preparing for the installation of the drainage system on basement B4
- Electrical system:
- Installing conduit on 11th and 12th floor
- Construction and installation of conduit on the basement ceiling B4, B3
- Construction and installation of conduit on the basement ceiling on the 7th and 8th floor
- Construction of cable tray in the office area on the 5th and 6th floor
- HVAC system:
- Transporting and processing of ductwork for the office area on the 5th floor
- Transporting and processing of ductwork in the basement office area B4
Some pictures of the project:
TBM daily at the project
Materials are arranged at the working area
Installation of embeded conduit/ Installation of the above ceiling conduit
Sleeve work preparation/ Duct work preparation
Other articles